UM Completes Relocation to the New Campus

1:binary?id=93CBn6JUj6dC1Ql97BU9seLE_2BGiLBrCf58oo8ph2wrKGrlG0kG0doQ_3D_3D:Over 50,000 boxes were used for packing during the relocation
Over 50,000 boxes were used for packing during the relocation
Photo Download
2:binary?id=93CBn6JUj6dC1Ql97BU9seLE_2BGiLBrCfhikRsBm3NGiOKds_2BuU5EcA_3D_3D:Moving large laboratory equipment is a challenging task
Moving large laboratory equipment is a challenging task
Photo Download
3:binary?id=93CBn6JUj6dC1Ql97BU9seLE_2BGiLBrCfcqaSAG44U46I5LMUY1cMDA_3D_3D:The Smart Environment and Cybernetics System Laboratory, the first laboratory to move to the new campus.
The Smart Environment and Cybernetics System Laboratory, the first laboratory to move to the new campus.
Photo Download
4:binary?id=93CBn6JUj6dC1Ql97BU9seLE_2BGiLBrCfSfhgUqKDSNPkDDohFXc5Rg_3D_3D:Workers are handling the statue
Workers are handling the statue
Photo Download
5:binary?id=93CBn6JUj6dC1Ql97BU9seLE_2BGiLBrCfY60Z_2B2GCRev2th5lNxibRg_3D_3D:UM completes relocation, and officially starts offering classes on the new campus in the 2014/2015 academic year
UM completes relocation, and officially starts offering classes on the new campus in the 2014/2015 academic year
Photo Download

Source: umagazine

The University of Macau’s (UM) new campus marks a milestone in higher education development in Macao. After three years of construction, it became fully operational in the 2014/2015 academic year.

The new campus covers 1.09 square kilometres, and is 20 times larger than the old campus. UM’s relocation to the new campus was a challenging undertaking at an unprecedented scale. It would be hard to find in Macao’s neighbouring regions another case of institutional relocation approaching such a large scale, except perhaps the former Hong Kong International Airport, which was 25 per cent smaller in size than UM’s new campus. The UM relocation involved packing more than 50,000 boxes. This number alone provides some indication of the vast amount of work involved in the process. How did UM manage to complete this challenging task without disrupting teaching and administrative activities?

Good Coordination Ensures Orderly Relocation

UM established an interim Relocation Workgroup (the Workgroup) soon after the Macao SAR government announced the new campus project in 2009. Led by UM Vice Rector (Administration) Dr Alex Lai, the Workgroup was responsible for the planning, coordination and implementation of the relocation plan. In early 2013, each of the 78 units at UM appointed a contact person to liaise with the Workgroup, to provide supplementary information and collect feedback regarding the relocation plan, to coordinate logistics and distribution work in the relocation process, and to arrange for colleagues from different units to participate in specific relocation-related tasks.

Throughout the process of preparing for the relocation, the Workgroup maintained close liaison with the various units to better plan the relocation schedule. To carry out the relocation more effectively, the Workgroup established nine teams to coordinate efforts of different functional units, including academic units, academic support units, administrative units, the library, labs, computer rooms, student dormitories, residential colleges, student organisations, staff hostels, public spaces, and sports facilities.

Such a complicated project required a systematic plan. The fact that there are so many units at UM added to the difficulty in communication and coordination. Peter Fung Woon Kee, one of the core members of the Workgroup, says, “Each unit appointed a representative to coordinate the relocation of his or her own department. These unit representatives also served as a bridge of communication between their units and the Workgroup. All the colleagues knew about the relocation plan beforehand and so everyone was fully prepared. All they waited was for the relocation date to be confirmed so they could carry out the relocation plan.”

No Precedent to Draw Experience From

Because there was no precedent in modern Macao history for relocation at such a large scale, the Workgroup visited other places in China, trying, without much success, to gain experience from similar relocation projects. Cornelia Ho Ka Lei, another core member of the Workgroup, says, “The Workgroup visited the University of Hong Kong, hoping to learn what kinds of difficulties are likely to be encountered. But HKU’s situation was different. It never relocated in its entirety. Only some of its departments moved to a neighbouring teaching building. It turned out that no other sizable university in China ever moved to a new campus in its entirety within a relatively short period of time. So members of the Workgroup had no choice but to put themselves in the shoes of a user to anticipate what problems were likely to occur and which information needed to be obtained. A consulting firm provided information and expert opinions to us, but even this consulting company had never undertaken such a large project.”

The relocation was carried out in three stages, with the bulk of the work conducted in the summer holiday between June and August, six months after the Campus Development Office (CDO) and Campus Management Office (CMO) first moved to the new campus. “The CDO and CMO’s moving to the new campus first was very useful to the Workgroup, because each experience could reveal problems that hadn’t entered our consideration,” says Cornelia. “For example, we learned that it would be best to prepare different kinds of forms beforehand so we could have a detailed record of the items being moved, and in case of any discrepancy, we could find the missing box by going through such records. These small-scale exercises in relocation helped us identify areas for improvement, which in turn made the large-scale relocation smoother.”

 

Relocating in Stages

The relocation was conducted in three stages, between December 2013 and August 2014.

Stage 1: December 2013—January 2014

Part of the Rector’s Office, and the New Campus War Room (including the Campus Development Office, part of the Campus Management Office, and part of the Information and Communication Technology Office)

Stage 2: February—April 2014

The Faculty of Health Sciences, part of the Office of Sports Affairs, some labs of the Faculty of Science and Technology, some offices of the Faculty of Education and Faculty of Law

Stage 3: May—August 2014

Large-scale Relocation

 

Thoughtful Planning and Quick Response to Changes

In the early days of the relocation, UM established a relocation coordination centre. In addition to assisting the various units with their relocation, the relocation coordination entre also provided lost & found services and gave daily relocation briefings. Brandon Sim Wee Han, a member of the Workgroup, says, “You need to work with the various units to push relocation ahead but also need to set the priorities straight. Moreover, you need to monitor the progress of the various tasks, and collect, sort and analyse a large amount of data. So in the early days, the Workgroup already completed a lot of work behind the scenes.” Before the relocation, the Workgroup liaised with the various units about the actual relocation dates and worked with the moving company to make a relocation schedule and determine the relocation procedure before confirming the individual relocation dates with the various units. In the meantime, the Workgroup made all other necessary preparations, including making videos to demonstrate how to properly pack items, and establishing guidelines on how to safely move items and handle confidential files. The Workgroup then uploaded the videos and guidelines to the UM website for easy access by all faculty members, students and staff.

Every exercise in relocation was a test of the Workgroup’s ability to quickly respond to changes. The fact that the relocation plan had to be constantly adjusted according to the actual date when each building passed quality inspection made it more difficult for the Workgroup to set the official move-in date, and for this reason the Workgroup made several contingency plans. “We have had several different versions of contingency plans,” says Cornelia. “Luckily, we didn’t meet any major setbacks, such as typhoons or storms, and we didn’t find ourselves in a situation where a building couldn’t become operational.”

The Workgroup consisted of representatives from the various units, most of whom didn’t have experience with moving or logistics management, so it was a steep learning curve for many involved in the process. “Each time before we moved something to the new campus, we would consider worst-case scenarios, and we would make a crisis response checklist,” Brandon says. “For example, what if the moving trucks broke down on the way? So we requested the moving company to have backup trucks on standby just in case.”

Safety Paramount, Zero Unexpected Events

Safety was the overriding concern for the Workgroup throughout the process of relocation. To ensure the safety of assets, safety of personnel, and security on the campus, the Workgroup made sufficient contingency plans. “There were many details to pay attention to,” says Peter. “Even after we gave the go-ahead to move, we would double check with the parties concerned to make sure that the building was truly ready for use in every way. Overall, the relocation was quite smooth, with zero unexpected events, and this made our hard work worthwhile.”

University-wide Cooperation Leads to Successful Relocation

The bulk of the relocation work was carried out in the summer holiday to minimise disruption of teaching and research activities, because there were relatively few students on the campus in the summer holiday. But this also meant that the relocation had to be completed on a very tight schedule. Foreseeing the possibility that some faculty members would not be in Macao at the time of relocation, the Workgroup prepared a sample written authorization to provide maximum convenience for these faculty members. Those who would be absent at the time of relocation only needed to pack their personal effects before leaving Macao and their representatives designated in the written authorisation would take care of the moving for them. Also, considering that some students remained on campus during the summer holiday, the Workgroup tried its best to prevent the relocation from causing interruption of services to students. “Before any unit moved to the new campus, it would send an email notification to the university community telling everyone when and for how long its services would be interrupted,” says Peter. “Some units, such as the Registry and the Finance Office, went one better—they had one or two colleagues move to the new campus first to minimise the down time caused by the entire department’s moving. Some decided to move on the weekends. Some even managed to maintain normal operation on both campuses during the relocation.”

The computer rooms on the old campus gradually stopped opening, and what needed to be disassembled, packed, moved, unpacked, and re-assembled within the shortest time possible included 3,278 computers, over 10,000 computer accessories and peripherals, 70,000 network access points, and innumerable electronic locks. Great care was taken during the transport. Anticipating future needs, the university also bought some new computers to make sure that computer services were still available during the relocation process. At the same time relocation was going on, preparations were made for the new semester.

Within just a few months, all the units at UM successfully completed the difficult task of relocating to the new campus by following the principle of “moving in stages and in batches”. The success was made possible by the university’s ability to quickly adjust the relocation plan according to changing circumstances as well as the unreserved support and cooperation from all UM members.


17/02/2015